Fire hydrant flow test with a pitot gauge

Fire line hydrostatic test, Charlotte

Last verified Nov 6, 2026 · Reviewed by Sarah Johnson

Sample photo

Items checked
5
Common fails
4

A new underground fire line is pressure-tested before it is covered and connected. The fire marshal and the water utility usually both need to see it pass.

What the inspector checks

  • Pipe, fittings and thrust blocks match the approved plan
  • Test pressure held for the required time
  • Joints exposed and dry
  • Flushing completed
  • Backflow preventer installed as approved

Common reasons it fails

  • Pressure drop during the test
  • Joints already buried
  • Flushing not done or not documented
  • Wrong backflow assembly

How to schedule

Request it from the fire inspector and coordinate the utility's witness; leave joints uncovered [check current process].

Related question: Do I need a fire hydrant flow test for a commercial project in Charlotte?