Erosion control for a 12-lot mountain subdivision
Buncombe County, NC · Residential developer
Sample photo · Sample project. Details changed.
- days, start to permit
- 49
- rounds of comments
- 1
- agencies, in order
- 1
The problem
The first plan had no phasing, so the whole site would have been open at once on a steep slope.
What we did
Agreed three grading phases with the design professional of record, who revised the plan.
Checked the basin and silt fence details against the county checklist.
Filed the plan and answered one comment on slope matting.
Set up the self-inspection log for the contractor.
Agencies, in order
- Buncombe Countyland disturbance permit
Outcome
Land disturbance permit issued after one round of comments, 49 days after we started.
Phasing the grading, which is what a steep site review looks for first.
Documents in the package
- Phased erosion and sediment control plan
- Sediment basin detail
- Self-inspection log