
Water tap for a new medical office
Cary, NC · Site contractor
Sample photo · Sample project. Details changed.
- days, start to permit
- 52
- rounds of comments
- 1
- agencies, in order
- 2
The problem
The utility plan showed the fire line but not the backflow assembly location, and the street cut had no traffic control plan.
What we did
Checked the utility plan against the town's tap checklist.
Had the design professional of record add the backflow assembly detail.
Had our licensed partner add a one-day traffic control plan for the street cut.
Filed the utility permit and the right-of-way permit together.
Answered one comment on restoration and booked the tap inspection.
Agencies, in order
- Town of Caryutility permit
- Town of Caryright-of-way permit
Outcome
Permits issued after one round of comments; the tap was inspected 52 days after we started.
Catching the missing backflow detail before filing instead of after the first review.
Documents in the package
- Utility plan with backflow detail
- Traffic control plan
- Street restoration detail