Restaurant build‑out to TCO and CO

Cary, NC · Tenant build-out contractor

Sample photo · Sample project. Details changed.

days, start to permit
44
rounds of comments
0
agencies, in order
3

The problem

Inspections were being booked one at a time. Two failed for items that could have been checked the day before.

Before us
Inspections booked one at a time · two failed
With us
Issued with no comments · 44 days

What we did

  1. Built one closeout list across every open permit and inspection.

  2. Walked the space before each inspection with the superintendent.

  3. Sequenced the fire and utility sign-offs ahead of the TCO request.

  4. Requested the TCO, then cleared the remaining items for the final CO.

Agencies, in order

  1. Town of Carybuilding inspections
  2. Town of Caryfire inspection
  3. Town of Caryutilities (grease interceptor)

Outcome

TCO issued 16 days after we started; the restaurant opened on its planned date. Final CO followed four weeks later.

Walking the space the day before every inspection, and doing the sign-offs in the order the TCO needs them.

Documents in the package

  • Closeout tracker
  • Inspection readiness checklists
  • TCO request