Water and sewer trench in the street in front of new townhomes

Water and sewer for 18 townhomes

Charlotte, NC · Residential developer

Sample photo · Sample project. Details changed.

days, start to permit
42
rounds of comments
1
agencies, in order
2

The problem

The utility and right-of-way packages had been filed separately with different work dates.

What we did

  1. Lined up the utility and right-of-way packages on one schedule.

  2. Had our licensed partner add an overnight plating plan to the traffic control plan.

  3. Answered one utility comment on the cleanout locations.

Agencies, in order

  1. Charlotte Waterservice connections
  2. City of Charlotteright-of-way permit

Outcome

Both permits issued the same week, 42 days after we started.

One schedule for two agencies, so neither waited on the other.

Documents in the package

  • Utility service plan
  • Traffic control and plating plan
  • Comment response letter