Sidewalk and curb ramps for a mixed-use building
Raleigh, NC · General contractor
Sample photo · Sample project. Details changed.
- days, start to permit
- 53
- rounds of comments
- 0
- agencies, in order
- 1
The problem
The schedule left two weeks for the permit, and the detour route crossed a bus stop.
What we did
Had our licensed partner move the detour so it kept the bus stop open.
Checked both ramps against the city's standard details.
Filed one package with the closure and the ramps together.
Agencies, in order
- City of Raleighright-of-way permit
Outcome
Permit issued with no comments 14 days after filing; the pour started on schedule.
Solving the detour before the city had to ask about it.
Documents in the package
- Right-of-way permit application
- Curb ramp details
- Pedestrian detour plan