New commercial driveway being finished on a flat four-lane state road, with drums and an arrow board

New commercial driveway on a state road

Raleigh, NC · Commercial developer

Sample photo · Sample project. Details changed.

days, start to permit
65
rounds of comments
1
agencies, in order
2

The problem

The client had filed with the City first. The package came back twice: the City asked for the NCDOT approval, and the traffic control plan did not match the lane being closed.

Before us
Filed with the City first · returned twice
With us
Issued after 1 round · 65 days

What we did

  1. Confirmed that US-70 is state-maintained and that NCDOT reviews the driveway first.

  2. Had our licensed partner revise the site plan with sight distance, driveway width and radii called out.

  3. Had our licensed partner redraw the traffic control plan for the actual lane and work hours.

  4. Filed the NCDOT driveway permit, then the City right-of-way permit with the NCDOT approval attached.

  5. Answered one City comment on the sidewalk detail and scheduled the inspections.

Agencies, in order

  1. NCDOTdriveway permit
  2. City of Raleighright-of-way permit

Outcome

City permit issued after one round of comments, 65 days after we started.

Filing in the right order. The City cannot finish its review without the NCDOT approval, so that came first.

We'd lost two months going back and forth. Once the order was right, it moved.
Sample client note

Documents in the package

  • Site plan with driveway geometry
  • Traffic control plan
  • NCDOT driveway permit application
  • Comment response letter