The cost of a stalled site: a simple downtime calculator

By Sarah Johnson · September 21, 2026 · 1 min read

Sample photo

A permit fee is a few hundred dollars. A crew waiting on that permit costs thousands a day. Put your own numbers in and see what a week of delay really costs.

When a permit package comes back with comments, the cost on paper is small: a resubmittal fee, a few hours of drafting. The real cost is in the field. A crew that was booked for Monday either waits, gets moved to another job at a loss, or leaves for a contractor who has work ready. Equipment sits. The schedule behind this job slides too.

$2,200
per day for a 5-person crew and equipment (sample)

Run your own numbers

Use the calculator below with the numbers from your own job. It is deliberately simple: crew size times the daily cost per person, plus equipment, times the number of days lost. It leaves out overhead, financing, liquidated damages and the jobs you could not start, so the real number is usually higher.

Downtime calculator

Cost per day
$2,200
Cost of the delay
$22,000

What the number tells you

Take a common case: a five-person crew at $320 a day each, plus $600 a day of rented equipment, waiting ten working days for a resubmittal. That is $22,000 of cost that buys nothing. A permit fee on the same job might be $250.

This is why preparation is cheap. An hour spent confirming which agency owns the street, or checking a traffic control plan against the posted speed, is worth more than any shortcut later.

Nobody budgets for waiting. That is why it always costs more than the permit.

Where the days come from

Most delay is not review time. It is the time between rounds: waiting for a design revision, chasing a signature, discovering that NCDOT needs to approve first, rebooking an inspection. Each round adds the reviewer's queue again. A complete first submittal removes most of those gaps.

Protecting the schedule

Put permits on the schedule as real tasks with real lead times. Do not mobilize until the permit is issued. Keep one person responsible for every open permit. And check every package against the comments that usually come back before it is filed. That is the work we do: we cannot decide for the agency, but we can make sure nothing in the package slows the decision down.