Driveway permit in the City of Raleigh right-of-way
Last verified November 12, 2026 · Reviewed by Sarah Johnson
Sample photo
- Agencies
- 2
- Typical weeks (sample)
- 6–12
- Documents
- 6
- Inspections
- 2
- Last checked
- November 12, 2026
Short answer
Yes. A new or widened driveway in the City of Raleigh right-of-way needs a city right-of-way permit. If the street is a state road maintained by NCDOT, the NCDOT driveway permit comes first and the city permit follows.
Agencies, in order
- NCDOT: driveway permitState road only
- City of Raleigh: right-of-way permit
Documents checklist
PreparedForYes1
- NCDOT driveway permit application and follow-up (state roads only; NCDOT decides)
You2
- Property owner's authorization
- Contractor licence and insurance certificate
Your design professional of record1
- Site plan with driveway width, curb cut and sidewalk
Licensed partner2
- Traffic control plan for work in the street
- Sealed detail where the plans call for one
Steps
- Confirm who maintains the street: NCDOT or the City.
- On a state road, apply for the NCDOT driveway permit first and wait for approval.
- Prepare the city right-of-way application with the site plan and traffic control plan.
- File with the City of Raleigh and answer review comments.
- Pay the fees, receive the permit and schedule inspections.
Inspections
- Forms and base, before the pour
- Final inspection of the driveway apron and sidewalk
Fees, reviewer comments and sources
Fees
- City right-of-way permit feeSource: City of Raleigh: right-of-way services[$___]
- NCDOT driveway permit fee (state roads)Source: NCDOT: driveway permits and encroachment agreements[$___]
Common reviewer comments
- Show the sight distance triangle at the driveway.
- Driveway width exceeds the maximum for this street.
- Provide the NCDOT approval before the city permit can be issued.
Sources
- City of Raleigh: right-of-way services · checked November 12, 2026
- NCDOT: driveway permits and encroachment agreements · checked November 12, 2026
Example content, not verified. Fees stay as [$___] until checked against the agency's current schedule.