Fire hydrant flow test with a pitot gauge

Fire line connection and flow test in the City of Raleigh

Last verified November 14, 2026 · Reviewed by Sarah Johnson

Sample photo

Agencies
2
Typical weeks (sample)
4–10
Documents
5
Inspections
2
Last checked
November 14, 2026

Short answer

Yes. A new fire line off the public water main needs a flow test, an approved fire line plan and a connection permit. The flow test results go into the fire sprinkler design, so it comes first.

Agencies, in order

  1. NCDOT: encroachment agreement for the tap in a state roadState road only
  2. City of Raleigh: water and fire line connection permit

Documents checklist

PreparedForYes2

  • Flow test request and results
  • Water and sewer availability letter request (the utility issues it)

You1

  • Contractor licence and insurance certificate

Licensed partner2

  • Fire line plan with backflow preventer and meter vault
  • Traffic control plan for work in the street

Steps

  1. Request the hydrant flow test and wait for the results.
  2. Give the results to the sprinkler designer and the design professional of record.
  3. File the fire line plan and connection application.
  4. Pay capacity and tap fees, then schedule the tap.
  5. Pass the pressure test and backflow inspection.

Inspections

  • Hydrostatic pressure test
  • Backflow preventer test and final

Fees, reviewer comments and sources

Fees
  • Flow test feeSource: City of Raleigh: water and sewer connections[$___]
  • Tap and capacity feesSource: City of Raleigh: water and sewer connections[$___]
Common reviewer comments
  • Flow test is older than allowed; provide a current test.
  • Show the backflow preventer location and access.
Sources

Example content, not verified. Fees stay as [$___] until checked against the agency's current schedule.