Utility cut permit in the City of Raleigh right-of-way

Last verified November 10, 2026 · Reviewed by Sarah Johnson

Sample photo

Agencies
2
Typical weeks (sample)
4–10
Documents
6
Inspections
2
Last checked
November 10, 2026

Short answer

Yes. Cutting the pavement or sidewalk for utility work in the City of Raleigh right-of-way needs a right-of-way cut permit. On a state road, an NCDOT encroachment agreement comes first.

Agencies, in order

  1. NCDOT: encroachment agreementState road only
  2. City of Raleigh: right-of-way cut permit

Documents checklist

PreparedForYes1

  • NCDOT encroachment agreement application and follow-up (state roads only; NCDOT decides)

You2

  • NC811 locate ticket
  • Contractor licence and insurance certificate

Licensed partner3

  • Utility plan and profile
  • Traffic control plan for work in the street
  • Pavement restoration detail

Steps

  1. Confirm who maintains the street and locate existing utilities.
  2. On a state road, get the NCDOT encroachment agreement first.
  3. Prepare the cut application with the utility plan and traffic control plan.
  4. File, answer comments and receive the permit.
  5. Restore the pavement and pass the final inspection.

Inspections

  • Open cut and backfill
  • Final pavement restoration

Fees, reviewer comments and sources

Fees
  • Right-of-way cut permit feeSource: City of Raleigh: right-of-way services[$___]
  • Pavement restoration depositSource: City of Raleigh: right-of-way services[$___]
Common reviewer comments
  • Show existing utilities near the cut.
  • Traffic control plan does not match the allowed work hours.
  • Pavement restoration detail is missing.
Sources

Example content, not verified. Fees stay as [$___] until checked against the agency's current schedule.