2
Typical weeks (sample)
4–10
Documents
5
Inspections
2
Last checked
November 8, 2026

Short answer

Yes. Utility and excavation work in the City of Asheville right-of-way needs a right-of-way permit. Many Helene rebuilding sites sit on state roads, where the NCDOT encroachment agreement comes first.

Agencies, in order

  1. NCDOT: encroachment agreementState road only
  2. City of Asheville: right-of-way permit

Documents checklist

PreparedForYes2

  • Erosion control measures for the work area
  • NCDOT encroachment agreement application and follow-up (state roads only; NCDOT decides)

You1

  • Contractor licence and insurance certificate

Licensed partner2

  • Plan of the work in the right-of-way
  • Traffic control plan for work in the street

Steps

  1. Confirm who maintains the street.
  2. On a state road, get the NCDOT encroachment agreement first.
  3. Prepare the city application with the plan, traffic control and erosion control.
  4. File, answer comments, receive the permit and schedule inspections.

Inspections

  • Work area and traffic control set-up
  • Final restoration

Fees, reviewer comments and sources

Fees
  • City right-of-way permit feeSource: City of Asheville: right-of-way permits[$___]
Common reviewer comments
  • Show the detour route for the lane closure.
  • Provide the NCDOT agreement number.
Sources

Example content, not verified. Fees stay as [$___] until checked against the agency's current schedule.