Right-of-way encroachment permit in the City of Asheville
Last verified November 8, 2026 · Reviewed by Sarah Johnson
Sample photo
- Agencies
- 2
- Typical weeks (sample)
- 4–10
- Documents
- 5
- Inspections
- 2
- Last checked
- November 8, 2026
Short answer
Yes. Utility and excavation work in the City of Asheville right-of-way needs a right-of-way permit. Many Helene rebuilding sites sit on state roads, where the NCDOT encroachment agreement comes first.
Agencies, in order
- NCDOT: encroachment agreementState road only
- City of Asheville: right-of-way permit
Documents checklist
PreparedForYes2
- Erosion control measures for the work area
- NCDOT encroachment agreement application and follow-up (state roads only; NCDOT decides)
You1
- Contractor licence and insurance certificate
Licensed partner2
- Plan of the work in the right-of-way
- Traffic control plan for work in the street
Steps
- Confirm who maintains the street.
- On a state road, get the NCDOT encroachment agreement first.
- Prepare the city application with the plan, traffic control and erosion control.
- File, answer comments, receive the permit and schedule inspections.
Inspections
- Work area and traffic control set-up
- Final restoration
Fees, reviewer comments and sources
Fees
- City right-of-way permit feeSource: City of Asheville: right-of-way permits[$___]
Common reviewer comments
- Show the detour route for the lane closure.
- Provide the NCDOT agreement number.
Sources
- City of Asheville: right-of-way permits · checked November 8, 2026
- NCDOT: driveway permits and encroachment agreements · checked November 12, 2026
Example content, not verified. Fees stay as [$___] until checked against the agency's current schedule.