Short answer
Yes. Digging in the Town of Cary right-of-way for utility work needs a right-of-way permit with a traffic control plan. On a state road such as NC 55, the NCDOT encroachment agreement comes first.
Agencies, in order
- NCDOT: encroachment agreementState road only
- Town of Cary: right-of-way permit
Documents checklist
PreparedForYes1
- NCDOT encroachment agreement application and follow-up (state roads only; NCDOT decides)
You2
- NC811 locate ticket
- Contractor licence and insurance certificate
Licensed partner2
- Utility plan with bore or open-cut method
- Traffic control plan for work in the street
Steps
- Confirm who maintains the street and call NC811.
- On a state road, get the NCDOT encroachment agreement first.
- File the town right-of-way application with the traffic control plan.
- Notify the town before work starts and restore the surface.
Inspections
- Backfill and compaction
- Final surface restoration
Fees, reviewer comments and sources
Fees
- Right-of-way permit feeSource: Town of Cary: right-of-way permits[$___]
Common reviewer comments
- Bore pits are too close to the edge of pavement.
- Work hours conflict with the school zone schedule.
Sources
- Town of Cary: right-of-way permits · checked November 11, 2026
- NCDOT: driveway permits and encroachment agreements · checked November 12, 2026
Example content, not verified. Fees stay as [$___] until checked against the agency's current schedule.