Our sample range is 3–6 weeks on a city street and 6–12 weeks when the street is a state road. Here is where the weeks go and which of them you control.
Contractors ask this before they ask the price, because the crew and the concrete are booked around the answer. The ranges on this site are sample figures: about 3–6 weeks for a driveway or sidewalk permit on a street the City maintains, and about 6–12 weeks when NCDOT maintains the street. Your job can fall outside them. The reasons are below.
Where the weeks go
Intake comes first: collecting the site plan, the owner's authorization, insurance and a description of the work. Then we assemble and check the package. Then the City reviews it. Most packages get at least one round of comments, which are answered and resubmitted. Then the permit is issued.
On a city street, the review and one round of comments take most of the time. Intake and assembly take days if the documents are ready, and weeks if they are not.
What a state road adds
Many main roads in Raleigh are maintained by NCDOT. On those, the state's driveway permit or encroachment agreement usually has to be approved before the City will issue its own permit. That is a second review by a second office, and it is why the range roughly doubles.
Find out who maintains the street on the first day. Filing with the City first on a state road is a common way to lose weeks.
The review clock belongs to the agency. The intake clock belongs to you.
What adds time
A returned package. If a required sheet is missing, the package comes back and waits in line again. In our sample figures one return costs about three weeks.
Lane or sidewalk closures. They need a traffic control plan that matches the street, prepared and sealed by a licensed partner.
Slow answers to comments. A reviewer's question that waits a week for your crew hours adds a week.
Other approvals that must come first, such as a site plan or a tree permit.
What you control
You control intake. Send the site plan, the signed owner's authorization and the insurance certificate together, and the package can be assembled in days.
You control how fast comments are answered. We draft the responses and tell you which ones need you. The same day is the target.
You do not control the review. Nobody outside the agency does, and nobody can promise you a date for it.
When to book the crew
Book the crew when the permit is issued. Filed means the agency has the package. It does not mean anyone has read it. If you have to plan earlier, plan against the long end of the range and keep the booking movable.