What goes into an encroachment package for utility work in a state right-of-way, who provides each item, and the usual reasons a package is returned.
Water, sewer, gas, power and telecom lines in a state-maintained right-of-way need an encroachment agreement with NCDOT before work starts. The agreement is between NCDOT and the owner of the line. The contractor usually does the legwork.
This is a general checklist. District offices keep their own lists and change them, so confirm the current one with the district that covers your road before you file.
From the utility owner or contractor
The agreement form, signed by the party that will own and maintain the line. If that is a city or a utility company, allow time for their signature.
A description of the work: what is being installed, where, how, and roughly when.
A utility locate ticket for the work area.
A certificate of insurance, and a bond if the district asks for one.
The property owner's authorization, where the work touches private land.
From a licensed partner or your design professional
A plan view showing the right-of-way lines, the edge of pavement, existing utilities and the new line with distances.
A profile for every crossing, with depths.
A pavement and shoulder restoration detail for anything that is cut.
A traffic control plan for the work zone, matched to the road's speed and lane layout.
Drawings and anything that needs a seal are prepared and sealed by a licensed partner or your own design professional of record. We do not produce them ourselves.
A complete package is boring to review. That is the goal.
From us
A check of the package against the district's current list before it is filed. The cover letter and the filing itself. Follow-up with the reviewer, and drafts of the answers to comments. Status for each agreement in the client portal.
Usual reasons a package is returned
The agreement is signed by the contractor, not by the owner of the line.
The right-of-way lines are missing from the plan, or the drawing has no scale.
There is no profile, or the profile gives no depth under the pavement and ditch.
The traffic control plan is a standard sheet that does not fit the road.
The restoration detail is missing for an open cut.
The work described in the letter does not match the drawings.
Before you file
Read the package as the reviewer would, with only the paper in hand. Can they tell what is being built, where it sits in the right-of-way, how traffic is handled and who owns the line afterwards? If any answer needs a phone call, the package is not ready.
After filing, review time belongs to NCDOT. Our sample range for the state review is 3–8 weeks. Book the crew when the agreement is approved.