NCDOT encroachment agreement for utility work on a state road
Last verified November 20, 2026 · Reviewed by Sarah Johnson
Sample photo
- Agencies
- 1
- Typical weeks (sample)
- 4–10
- Documents
- 7
- Inspections
- 2
- Last checked
- November 20, 2026
Short answer
Yes. Water, sewer, gas, power, fiber or telecom lines placed in, under or across a state road right-of-way need an NCDOT utility encroachment agreement, whether the crossing is bored or open cut. The agreement must be executed before work starts, and it comes before any city or county permit for the same work.
Agencies, in order
- NCDOT: utility encroachment agreement
Documents checklist
PreparedForYes1
- Encroachment package assembled, filed with the district and followed up (NCDOT decides)
You3
- Encroachment agreement form, signed by the utility owner
- NC811 locate ticket
- Bond or insurance certificate, where the district asks for one
Licensed partner3
- Utility plan and profile showing the line, depth and distance from the pavement
- Bore or open-cut detail, with the pavement restoration detail for open cuts
- Traffic control plan for work in the street
Steps
- Confirm the road is state-maintained and find the NCDOT district office.
- Confirm who owns the line. The agreement is signed by the utility owner, and sometimes by the contractor and the city as well.
- Prepare the plan, the crossing detail and the traffic control plan.
- Submit the encroachment package to the district and answer comments.
- Wait for the executed agreement before any work in the right-of-way, and keep a copy on site.
- File the city or county permit, if one applies, with the NCDOT approval attached.
- Give the district notice before starting and call for the final inspection.
Inspections
- District inspection during the crossing, where the agreement requires it
- Final inspection of the restoration and the shoulder
Fees, reviewer comments and sources
Fees
- Encroachment review fee, where it appliesSource: NCDOT: driveway permits and encroachment agreements[$___]
- Bond amount, where the district asks for oneSource: NCDOT: driveway permits and encroachment agreements[$___]
Common reviewer comments
- Show the depth of cover under the pavement and the ditch line.
- Bore the crossing; an open cut is not accepted on this road.
- Traffic control plan does not match the lane closure shown on the plan.
- The utility owner's signature is missing on the agreement.
Sources
- NCDOT: driveway permits and encroachment agreements · checked November 12, 2026
Example content, not verified. Fees stay as [$___] until checked against the agency's current schedule.