Short answer
Usually. Grading above the county threshold needs an approved erosion and sedimentation control plan before any land is disturbed. Steep slopes in Buncombe County get extra review.
Agencies, in order
- Buncombe County: grading and erosion control permit
Documents checklist
PreparedForYes1
- Construction stormwater (NPDES) coverage application (the state issues it)
You1
- Financial responsibility form
Licensed partner2
- Erosion and sedimentation control plan
- Slope analysis for steep sites
Steps
- Measure the disturbed area and the slopes.
- Prepare the erosion control plan.
- File with the county and answer comments.
- Install measures before grading and keep the inspection log.
Inspections
- Measures installed before land disturbance
- Final stabilization
Fees, reviewer comments and sources
Fees
- Plan review fee, per disturbed acreSource: Buncombe County: erosion control[$___]
Common reviewer comments
- Slope stabilization is missing for slopes steeper than allowed.
- Sediment basin is undersized for the drainage area.