Do I need an NCDOT encroachment agreement for a utility cut on a state road?

Last verified Nov 5, 2026 · Reviewed by Sarah Johnson

Sample photo

Answer
Yes
Steps
6
Related guides
2

Short answer

Yes. Utility work inside an NCDOT right-of-way needs an encroachment agreement before work starts. The city may also need its own right-of-way or cut permit after NCDOT approves.

Which permit comes first

Is the street maintained by NCDOT?

YesNCDOT permit first, then the city permit

NoCity right-of-way permit only

Steps

  1. Confirm the road is state-maintained.
  2. Prepare plans showing the cut, depth, bore or open cut, and the restoration detail.
  3. Add a traffic control plan for the lane or shoulder closure.
  4. Submit the encroachment agreement to the NCDOT district office.
  5. After NCDOT approval, file the city right-of-way permit if the city requires one.
  6. Schedule the restoration inspection when the work is done.